ALGERIA: MOSTAGANEM TRAMWAY
				Client
Entreprise Metro d'Alger
Sous-système
Durée du projet
2013 - ongoing
Description
The first tramway line of Mostaganem, 14.2 km long, is composed of 2 sections:
- The first section connects the « Salamandre » sector to the « Kharouba » sector, 12.2 km long and with 20 stations.
 - The second section connects the SNTF station to the new bus station, 2 km long and with 4 stations.
 
périmètre du projet
The evaluation covers the following phases:
- Phase 1: Design of the installations and manufacturing of the equipment
 - Phase 2: Manufacturing – Installation
 - Phase 3: Tests and trials
 - Phase 4: Preparation for operation
 - Phase 5: Commissioning (Safety file)
 - Phase 5.1 Partial safety file
 - Phase 5.2: Completion of the safety file
 
Réalisations
						
										Voir tout