ALGERIA: ORAN TRAMWAY
Cliente
Entreprise Metro d'Alger (EMA)
Sottosistema
Durata del progetto
2007 to 2013
Descrizione del progetto
Our Service
- Global coherence, system approach
 - Operation of tramways
 - External risks, natural risks and technological risks
 - Command and control, railway signalling
 - Civil engineering -Solidity
 - Platform, track and switches and crossings
 - Traction energy, 11 substations including 1 in depot
 - Rolling stock: 30 Citadis 302 trainsets
 - Urban integration
 - 32 stations including 4 interconnections, cameras at intersections
 
CERTIFER team
1 project manager and 10 experts
Ambito di lavoro
Risultati
						